Bridge Project

Project Description: 
Grading and bridge replacement 

Crow Wing County is actively planning to replace the bridge at the Rabbit Lake Landing on County State Aid Highway 30.  The current bridge was installed after the closing of the Kennedy Mine.  The bridge has met the engineering life span and is being replaced.  The new bridge have 12-foot lanes and 6-foot shoulders.  It will also be taller and wider for boat traffic.  

Crow Wing County Resources

You can stay up to date with the project by looking at the Crow Wing County Website link:

Future Projects | Crow Wing County, MN - Official Website

Project Schedule

Final Design: 2024-2025
Permitting: 2025
Right-of-Way Acquisition: September – December 2025
Project Letting: March 2026
Memorial Day: May 25, 2026
​Close Road/Implement Detour: May 26, 2026
Remove Old Bridge: End May 2026
New Bridge Construction: June – September 2026
Boat Restrictions Through Narrows: Periodically; dependent on MnDNR Permitting
Labor Day: September 7, 2026
Approach Panels & Approach Paving: September 2026 
Project Complete: September 30, 2026